To change a component to an alternate

You may want to change a component to an alternate to exclude its part/pricing information from the contract for your customer. By doing so the alternate will appear in the alternate list section of proposals and in Cost Status Reports if the status is defined as Accepted or Undecided and will be disregarded altogether if the status is defined as Declined. If the alternate is defined as Accepted its data will also be present in the Project Manage Summary Mode. However, the part information and costs will not be reflected in the project specifications section of the proposals and base bid.

  1. Load the project for which you want to change an alternate to a component. This is done within the Customers Manager.
  2. Select the component that you want to change to an alternate from the Alternate/Component List.
  3. Click the Edit button beneath the Alternate/Component List.
  4. The Component will now open in the window. At the top of the screen click the Alternate side of the Component/Alternate switch.
  5. Click the Save button.
  6. Click the Close button to return to the Project contents. Notice that the part information that was previously contained in the alternate is now displayed in the Project Manager main window.

See Also

Basic Operations

To change a project title

To change a project description

To add parts to a project

To add an alternate to a project

To delete an alternate

To edit an alternate

To add a component to a project

To delete a component

To edit a component

To change an alternate to a component

To refresh the prices of a project

To view the time card totals

To change a project's markup